| School Location: | Bharamasagara village, Chitradurga taluk and district, Karnataka |
| No. of Students: | 595 |
| Grades: | Classes LKG to 8th (Kannada and English medium) |
| Requirements: | The school totally required 18 classrooms and few more rooms for office room, staff room, labs, library, etc. The school had only 16 good rooms. |
| OSAAT Proposal: | OSAAT constructed 5 classrooms. |
| Estimated Cost: | INR 75 L (USD 89K) |
| Funding: | This project was funded by donors in India and USA. |
| Status: | Construction started with the ground- breaking ceremony on 24-Jan-2025, completed with the handing over of the new building on 27-Oct-2025. |