School Location: | Rajakatti village, Hukkeri taluk, Belagavi district, Karnataka |
No. of Students: | 276 |
Grades: | 1st to 7th (Kannada medium) |
Requirements: | The school needs minimum 7 classrooms and an office room. A Mangalore tile roofed building has collapsed during the heavy rains in Aug-2019. They do not have any good classrooms. Government is now building 3 classrooms. The toilets are in average condition. |
OSAAT Proposal: | Construction of 3 classrooms and a toilet block for boys and girls |
Estimated Cost: | INR 40 lakhs (USD 55K) |
Funding: | This project was adopted by donors from India |
Status: | Construction started with the ground breaking ceremony on 06-Nov-2020, completed with the inauguration on 15-Dec-2021. |